Fish Hawk Landing Ground work

Hello Fish Hawk family! Hope everyone had a fantastic Memorial Day weekend! Things are moving along great down here and will only get better with summertime weather right around the corner. Here is our weekly update:

Building 1: Foundation work is done and we’re now going vertical! First floor framing is near completion and we’ll be rolling the second floor joists this upcoming week. Second floor framing will follow soon after.

Building 2: Underground plumbing is currently underway and will be completed soon. Slab prep will be next followed by spray foam under-slab insulation. Slab pour isn’t far off so make sure you are all ready for your second additional deposit.

Building 3: Mass excavation is completed and we will soon be ready to begin our foundational work starting with the forming of the footers.

Building 4: Mass excavation is currently in progress and will be completed soon.

Building 6: Interior party walls have been poured, initial slab prep is completed, and underground plumbing will follow soon after.

Fish Hawk Landing Foundations poured
Fish Hawk Landing Framing
Fish Hawk Landing Excavation