Happy Friday Fish Hawk family! Here is our weekly update:
Building 1: The floor joists have been rolled and we’ve begun framing on the main floor. Upper floor framing will begin next week, to be followed by trusses and roof framing. After all the dirt work we’ve done this winter and spring it’s very exciting to see these buildings finally going vertical!
Building 2: Underground plumbing is near completion. Will be going for underground plumbing inspection early next week. Just a friendly reminder again to be ready for your second additional deposit, which will be due at slab pour.
Building 3 & 4: Mass excavation continues. We are currently in a holding pattern as run-off ground water subsides. All this nice weather we have in the upcoming week, and hopefully weeks to follow, should help us to continue moving along swimmingly in our excavation and foundation work.
Building 6: Foundation is prepped and ready for underground plumbing which will begin as soon as we are done with undergrounds at building 2.
Have a fantastic weekend everyone!