Happy Friday Fish Hawk family! Here is our weekly update:

Building 1: Framing of the main floor has been completed and we’re near completion on the upper floor framing. Roof framing will follow soon after.

Building 2: Underground plumbing is completed and has passed inspection. Under-slab spray foam insulation has wrapped up and the next step will be to run our in-slab radiant heat lines. Slab pour will be soon, just another reminder to make sure you’re all ready for your second additional deposit.

Building 3 & 4: With all the nice weather we’ve had this past week we’ve seen the run-off subside substantially. We’ll soon be moving on to prepping for the footers. 

Building 5: Currently clearing material and trailer off the lot for building 5. Will begin our excavation work soon.

Building 6: We’ll start our underground plumbing this upcoming week. Slab prep will follow soon after. Just an early heads up that your second additional deposits will be coming up soon.

Have a great weekend everyone!

20220603 152018
20220610 151004
20220610 152527
20220610 152631

Filed Under: Fish Hawk Landing News

Copyright © 2023 Fish Hawk Landing

The developer reserves the right to change interior and exterior finishes.