
Hope everyone had a fantastic week! Here’s our weekly update for Fish Hawk Landing:
Building 1: Trusses have been set and roof framing is currently in progress. Roof framing will wrap up early next week to be followed by dry-in.
Building 2: In-slab radiant heat lines have been run and passed inspection. Slab will be poured sometime next week. One more reminder that your second additional deposit will be due at slab pour. After the slab has cured we will start going vertical with framing.
Building 3: Ground water has subsided and we’ll be getting back to prepping on this unit next week. Utilities will be finished soon.
Building 4: Water has also subsided at building 4 and foundation will be dug after utilities are finished up at building 3.
Building 5: We will begin on utilities here once excavation is complete at buildings 3 and 4.
Building 6: Underground plumbing is currently in progress. Once wrapped up we will begin our initial prep for slab pour. Just another reminder that second additional deposits will be due at slab pour.
Enjoy your weekends everyone!


