It’s Friday Fish Hawk family! Hope everyone had a great week! Things have been bustling down here at Fish Hawk Landing and we’re on the verge of going vertical at our second building! Here’s the weekly update:
Building 1: Roof framing is wrapping up and framers are moving on to setting the timbers. Dry-in will be next followed not long after by plumbing and electrical rough-ins.
Building 2: The slab’s been poured and has had time to cure. Framers are currently working on their layout and we’ll start going vertical on our second building soon!
Building 3: Utility work is wrapping up. We’ll be moving on to mass excavation and foundation work soon.
Building 4: The foundation has been dug and we’re ready for our concrete crew to starting forming footers next week.
Building 5: Trailer and building material has been moved off the lot and we will begin our utility work once mass excavation concludes at building three.
Building 6: Underground plumbing has wrapped up and passed inspection. The slab’s been prepped and under slab spray foam insulation is completed. Slab pour will likely be sometime next week. Last reminder that second additional deposits will be due at slab pour.
Bust out your umbrellas and ponchos, going to be a wet one in Summit this weekend! Hope everyone stays dry and enjoys their weekend!