Friday is here Fish Hawk Family! Dust off your bottle rockets and sparklers, it’s 4th of July weekend! We’ve just finished pouring 3 out of our 6 foundation slabs and things are rockin’ down here! Here is our weekly update:
Building 1: Roof framing has wrapped up and timber framing will continue into next week. The dry-in process has begun with the installation of roof underlayment wrapping up today. Plumbing rough-in will follow soon after.
Building 2: We’re going vertical at our second building! First floor walls are completed and the main level subfloor is currently in progress. Second floor framing will be next.
Building 3: Utility work has wrapped up. We’ve begun our foundation excavation which should be completed by the middle of next week. Prep for footings will be next.
Building 4: Concrete footers have been formed and poured. Forms will be pulled next week and the next step will be forming the foundation walls.
Building 5: Site has been pinned for utilities which will begin once excavation at building 3 is completed.
Building 6: The slab has been poured and it won’t be long before we’re going vertical at our third building. Framers will begin their layouts once roof framing at building 2 is wrapped up.
Enjoy your Independence Day everyone! Stay safe out there!