Happy Friday Fish Hawk Family! Here is our weekly update:
Building 1: Timber framing is on-going. Roof underlayment has wrapped up and our windows have been delivered, install will begin soon. Rough plumbing will get started this upcoming week.
Building 2: Main level walls are completed and the upper level subfloor has been laid. Upper level walls will continue into next week. Truss packs have been delivered and roof framing will begin as soon as the framing of the upper floor is completed.
Building 3: Mass excavation has completed and footers have been formed. Footers will be poured next week.
Building 4: Footer forms have been pulled and foundation walls have been formed. Walls will be poured next week along with the footers at building 3.
Building 5: Excavators will backfill building 4 after walls are poured and will move on to digging for utilities at building 5.
Building 6: Framers have finished layouts and first floor framing has begun at our 3rd building on site.
Have a great weekend everyone!