Happy Friday Fish Hawk Family! Here is our weekly update:
Building 1: Rough plumbing continues in unit 1. Once plumbers move to unit 2 we’ll have electricians begin their rough-in work at unit 1.
Building 2: Upper level subfloor and walls are on-going. After walls are finished we will move on to roof framing and setting timbers.
Building 3: Foundation walls and piers are formed and will be poured next week. After backfill we will move on to forming the interior footers.
Building 4: Backfill is next up on the schedule. To be followed by the interior footers.
Building 5: We have utilities pinned and will move on to digging after building 4 backfill is complete.
Building 6: Main level subfloor and walls have been completed. We will begin rolling joists on the upper level soon.
Enjoy your weekend everybody!