Happy weekend Fish Hawk Family! Hope everyone had themselves a nice relaxing week! Here is our latest update for Fish Hawk Landing:
Building 1: Rough plumbing has wrapped up at unit 1 and we’re currently running pipe at unit 2. Unit 2 should wrap up by the end of the week and we’ll be moving on to our final unit in building 1. Rough electrical will get started soon at unit 1.
Building 2: Upper level subfloor has been completed and walls will continue into next week. Once the upper level is wrapped up we will begin framing the roof and setting timbers.
Building 3: Walls and piers have been poured. We will backfill the foundation soon.
Building 4: Backfill will happen at buildings 3 and 4 as soon as excavators are available.
Building 5: After building 3 and 4 are backfilled we will move on to digging for utilities at building 5.
Building 6: Upper level subfloor is currently in progress. Next will be framing the upper level walls and then on to roof framing.
Keep your umbrellas and ponchos nearby, it’s going to be another week of rain up here in Summit County. Stay dry out there! Enjoy your weekend everybody!