Happy Friday everyone! Hope you all had a fantastic week. Here is our weekly update:
Building 1: Rough plumbing at unit 3 is in progress. Rough electrical has wrapping at unit 1 and will finish up next week. Rough electrical will dive into Unit 2 once they wrap up at Unit 1.
Building 2: Roof Framing is complete, and roofers already have it dried in. Window install as well as house wrap is in progress. Timber framing is in progress as well.
Buildings 3 & 4: Backfill is complete at building 3 and almost wrapped up at building 4. Once underground gas passes inspection backfill will be completed quickly.
Building 5: Once finished with building 4 utilities will start to go in for building 5.
Building 6: Upper level walls are in progress. Trusses will go in next week followed by roof framing.
Have a great weekend Fish Hawk family!