Another productive week in the books down here at Fish Hawk Landing. Here is our weekly update:
Building 1: Rough plumbing has wrapped up at unit 3 and building 1 now has all of its rough plumbing completed. Rough electrical is finished at unit 1 and will be moving on to unit 2 next week.
Building 2: The dry-in phase is moving along nicely, windows are currently going in and housewrap will be completed soon. Timber framing will continue into next week.
Buildings 3 & 4: Backfill has been completed at both buildings and interior footers have been poured and passed inspection. Initial slab prep will be next, followed by underground plumbing. Just an early reminder that second additional deposits will be due at slab pour.
Building 5: Now that we’ve finished backfill at buildings 3 & 4 we can move on to digging for utilities at building 5
Building 6: Upper level walls are completed and trusses are in. Roof framing will continue into next week. Housewrap has also begun to go on.
The summer of rain continues! Stay dry and have a great weekend everyone!