Happy Friday everyone! Hope you all had a great week! Here is our weekly update:
Building 1: Rough plumbing is finished at building 1. Rough electrical is moving on to the final unit. After electrical wraps up we will be looking to start running our in-floor radiant heat lines. Stone siding install will also begin soon.
Building 2: Rough plumbing will begin soon. The dry-in process continues with installation of windows and house wrap. Timber framing is also on-going.
Buildings 3 & 4: Interior footers and walls are poured and we’re ready for slab prep which will begin soon. Another reminder to homeowners that your second additional deposit will be due at slab pour.
Building 5: Building 5 utility work will begin shortly.
Building 6: Roof framing continues. The dry-in process has begun with house wrap going on and windows being installed.
Enjoy your weekend Fish Hawk family!