Finally, after a long wet summer we finally have a few nice sunny days upcoming in the forecast. Hope you all have enjoyed the sunshine and beautiful weather we’ve had out here this week. Here is our weekly update:
Building 1: Rough electrical continues at Unit 3. After rough electrical is wrapped up at Building 1 we will move on to laying in-floor radiant heat lines.
Building 2: Rough plumbing is getting started at unit 4. Window install and house wrap continues. Deck framing is also currently on-going.
Buildings 3 & 4: Slab prep has wrapped up. Underground plumbing will begin next week, followed by spray foam foundation insulation and installation of in-slab radiant heat lines. After that we will be looking to pour the slab. Just another reminder that second additional deposits will be due at slab pour.
Building 5: Now that slab prep is completed at Buildings 3 and 4 we will look to begin digging for utilities at Building 5 next week.
Building 6: Roof framing is nearing completion. Dry-in process continues with house wrap and window installation. After roof framing wraps up we will look to start waterproofing the roof.
More sunny days upcoming! Enjoy your weekend everyone!