Happy Friday! Here is our weekly update down at Fish Hawk Landing:
Building 1: Rough electrical is on-going at Building 1. Fireplace units have been installed in all three units.
Building 2: Rough plumbing continues at Unit 4. Deck framing is on-going. Window and house wrap installation is also still in progress.
Building 3: Underground plumbing is currently in progress, to be wrapped up next week. Spray foam insulation will be next. Another reminder that second additional deposits will be due at slab pour.
Building 4: Slab prep has been completed and we’ll start underground plumbing here once we’re finished at Building 3.
Building 5: Digging for utilities has begun. Foundation excavation will begin once utilities are in.
Building 6: Roof framing is still on-going, to be completed soon. Installation of windows and house wrap continues. Framers are currently touching up on small details inside the unit.
Have a great weekend everyone!