Hope you had a fantastic week. Here is our update this week.
Building 1: Rough electrical is nearing completion.
Building 2: Rough plumbing on unit 4 is nearing completion. Window install as well as house wrap is in progress. Deck framing is nearing completion.
Building 3: Underground plumbing is complete. Slab prep is complete as well. Underslab insulation is complete too.
Building 4: Underground plumbing is in progress.
Building 5: Utilities are complete. Foundation excavation is in progress.
Building 6: Roof framing is complete. Deck framing is still in progress.
Have an awesome weekend!