Hope you all have been enjoying the fall colors this week! Here is our weekly update down at Fish Hawk Landing:
Building 1: Rough electrical has wrapped up and passed inspection. In-floor radiant heat lines have been run and also passed inspection. Gypcrete pour will be next.
Building 2: Rough plumbing continues. Window install and house wrap are also on-going. Deck framing is close to being wrapped up.
Building 3: Under-slab insulation has been completed and in-slab radiant heat lines have been ran. Barring the weather, slab pour will be sometime next week. Final reminder that second additional deposits will be due at slab pour.
Building 4: Underground plumbing continues. To be followed by our initial slab prep. Just an early reminder that your second additional deposits will be due at slab pour.
Building 5: Footers have been formed and poured. Foundation walls are formed and ready to be poured early next week.
Building 6: Roof framing has wrapped up. Soffit is currently being installed. Deck framing is on-going.
Enjoy your weekend everyone!