Happy Friday Fish Hawk family! Here is our weekly update:
Building 1: Gypcrete has been poured in all three units. Insulation will begin next week.
Building 2: Rough plumbing is on-going. Rough electrical has begun at unit 4. The dry-in process will continue into the next couple week.
Building 3: Slab pour will be early Monday morning. One last reminder that your second additional deposits will be due at slab pour.
Building 4: Underground plumbing has wrapped up and passed inspection. Slab prep will be next. Another early reminder that second additional deposits will be due at slab pour.
Building 5: Foundation walls have been poured and forms have been stripped. Backfill will be next followed by work on the interior footers.
Building 6: Soffit install is on-going and framing back-out is currently in progress. Deck framing is also on-going.
Have a great weekend everyone!