Bust out your ice picks and shovels, wintertime is here in Summit County! Things are moving along steadily down here at Fish Hawk Landing. Here is our weekly update:
Building 1: Building 1 has passed framing inspection and we’re ready to begin the insulation process. We will start with air sealing which will be underway soon.
Building 2: Rough electrical continues in unit 5 and plumbing rough-in is now completed at building 2. All windows are now installed and the dry-in process has concluded.
Building 3: First floor wall framing has wrapped up, the second and third level subfloor has been completed, and framers will begin third level wall framing soon.
Building 4: Slab prep has finished and we’ll be moving on to under-slab insulation soon. Another reminder that second additional deposits will be due at slab pour.
Building 5: Building 5 has been backfilled and prepped for interior footers which will be formed and poured soon.
Building 6: Rough plumbing has begun at unit 16 in building 6.
Enjoy your week and stay warm everyone!