Hope everyone had a cozy warm week! Here is our weekly update:
Building 1: Insulation has wrapped up. Drywall has been stocked and hanging has begun. Drywall work will continue into next week with taping and mudding. Exterior siding continues to go up and is nearing completion.
Building 2: Rough electrical continues. Exterior siding is on-going.
Building 3: Roof framing has wrapped up and framers are currently working on backout framing. Tyvek housewrap has begun to go up, the dry-in process will continue over the next couple weeks.
Building 4: Under-slab spray foam insulation finished and the slab was poured. We will give the slab over the weekend to cure and then will begin going vertical at our 5th building at Fish Hawk Landing!
Building 5: The foundation has been backfilled and underground plumbing will begin next week.
Building 6: Rough plumbing is currently in progress at unit 17 and will be moving on to unit 18 soon.
Bust out the planks for some early season powder laps! It’s a winter wonderland out here! Drive safe, stay warm, and have an awesome weekend everyone!