Happy New Year everyone! Goodbye 2022, hello 2023! Hope you all had nice and relaxing holidays! Here is our weekly update for the first week of the new year:
Building 1: Drywall has been tape, mudded, and textured at units 1 & 2. Unit 3 will be drywall stocked soon. We will begin priming and painting at unit 1 next week. Exterior siding will be stained/painted when weather is nice enough to allow it.
Building 2: Electrical rough in is nearly completed in unit 6. After electrical wraps up we will begin insulation at unit 4 and work our way down to unit 6. Exterior siding will be stained/painted when weather is nice enough to allow it.
Building 3: Tyvek housewrap, sealing of penetrations, and exterior siding continues to go up. Rough plumbing has wrapped up at unit 7 and has moved on to unit 8. Exterior siding will be stained/painted when weather is nice enough to allow it.
Building 4: Layouts and 1st level framing has wrapped up, 2nd level floor trusses have been rolled and framing on the 2nd level walls has begun.
Building 5: Underground plumbing has wrapped up at all three units.
Building 6: Rough plumbing has wrapped up at building 6. Rough electrical will begin here as soon as it is finished at building 3. Exterior wall penetrations continue to be sealed and siding continues to go up. Exterior siding will be stained/painted when weather is nice enough to allow it.
Enjoy your weekend everyone!