Another productive week in the books down at Fish Hawk Landing. Here is our weekly update:
Building 1: Units 1 & 2 are now in the finishing stages of the build. Tile and trim carpentry will begin soon. Unit 3 has been drywalled and is now being taped and mudded.
Building 2: Rough electrical and plumbing is wrapped up and we will begin insulating soon.
Building 3: Rough plumbing continues at unit 8 and will move to unit 9 next week. Deck framing is currently on-going and exterior siding continues to go up.
Building 4: 3rd level subfloor has been laid and work on the 3rd level walls is currently on-going. Exterior drywall has begun being hung.
Building 5: Underground plumbing was delayed due to heavy snowfall, the final unit will be wrapped up soon. After that we will move to framing, insulating, and pouring the slab. Another early reminder that your second additional deposits will be due at slab pour.
Building 6: Rough electrical wrapped up at unit 16 and is now underway at unit 17.
Enjoy a nice relaxing weekend everyone!