Happy Friday everyone! Here is our weekly update:
Building 1: Thinset is down, cement board is up, and shower pans are poured. Tile work has begun at units 1 & 2 and should be wrapped up soon. Carpenters will begin setting cabinets next. Unit 3 walls have been textured and painters will be in there priming next week.
Building 2: Unit 6 has passed framing inspection and will begin insulation soon. Units 4 and 5 will follow soon thereafter.
Building 3: Rough plumbing is on-going at the final unit in building 3. Deck framing and exterior siding continues.
Building 4: 3rd level walls have gone up and trusses are currently being installed. After trusses are in we will begin roof framing.
Building 5: Underground plumbing has wrapped up and we will begin framing soon. After framing of the first floor is concluded we will look to insulate the slab, run in-slab heat lines, and pour the slab.
Building 6: Wire is currently being ran at unit 17. Rough electrical will move to the final unit in building 6 soon. Once electrical is finished we will begin insulation.
Stay warm and enjoy a snow filled weekend y’all!