Happy weekend Fish Hawk family! Here is our weekly update:
Building 1: Tile work on all bathrooms and fireplaces has wrapped up at building 1. Carpenters have finished setting cabinets in all three units and countertops have been templated and will be installed soon. Luxury vinyl plank flooring on the main level and upper level is installed, all that remains for LVP flooring is the lower level.
Building 2: Gypcrete on the main level and upper level has been poured at all three units. Insulation is nearly completed at the final unit and we will begin stocking drywall soon.
Building 3: Rough plumbing continues at unit 9. Rough electrical is on-going at unit 7 and will move to unit 8 once wrapped up.
Building 4: Roof framing has wrapped up and framers are currently working on their framing back-out. Windows are currently being installed and Tyvek housewrap is going up.
Building 5: Framing of the first floor has begun. After first floor framing is finished we will insulate the slab, run in slab-heat lines, and pour the slab. Another reminder that second additional deposits will be due at slab pour.
Building 6: Rough electrical has wrapped up at building 6. Gypcrete pour and insulation install will be next up.
Enjoy a nice relaxing weekend everyone!