
Happy Friday everyone! Here is our weekly update:
Building 1: Tile work has begun on kitchen backsplashes and will continue into next week. Carpenters have started installing trim beginning with the window sill. Doors are also currently being set. Almost all countertops have been installed and we will be looking to begin electrical & plumbing trim out soon.
Building 2: Insulation is completed at all three units. We will begin stocking drywall next week at unit 6.
Building 3: Rough plumbing is wrapping up at unit 9. Rough electrical has finished at unit 7 and is currently underway at unit 8.
Building 4: The dry-in process continues with windows currently being installed and Tyvek housewrap going up. Small framing adjustments are still in progress.
Building 5: Framing of lower level walls have finished. Main level floor is finished and walls are currently in progress.
Building 6: In-floor radiant heat lines are currently being installed. After completed we will look to pour gypcrete on the main level and upper level at all three units.
Have a good weekend gang!




