Friday is here! Hope you all had a great week! Here is our weekly update:
Building 1: With the kitchen backsplash tile now completed at all three units, tile work has wrapped up at building 1. Carpenters will continue trimming out the units over the next couple weeks. Shingle install is currently on-going.
Building 2: Drywall has been stocked at unit 6. Drywallers will begin hanging drywall next week.
Building 3: Rough plumbing continues at unit 9 and should be wrapped up sometime next week. Rough electrical is on-going at unit 8.
Building 4: Almost all windows are installed and Tyvek housewrap is up. Deck framing and timber framing will continue into next week.
Building 5: Main level walls have been framed, upper level joists are rolled, and framing on the upper level walls has begun.
Building 6: In-floor heat lines have been installed and gypcrete has been poured on the upper and main levels at units 16 and 17. Gypcrete pour will wrap up at unit 18 next week.
Have a great weekend everyone!