Buyer’s Update – March 17th, 2023

March 17, 2023 by Fish Hawk Landing

Units going up fast

Building 1: Carpenters continue their trim work and hanging doors. Metal roofing and shingles have been installed.

Building 2: Unit 6 drywall has been taped, mudded, and textured. Painters are currently prepping for priming walls and ceilings. Drywall is stocked and his begun being hung at unit 5.

Building 3: Rough electrical continues at unit 9. In-floor radiant heat lines have been installed and gypcrete has been poured at all three units. Insulation will be next up for building 3.

Building 4: Timber framing is on-going. Soffit continues to be installed and windows continue to go in.

Building 5: Roof framing is finished and framing back-out is currently in progress. We will look to start backfilling the foundation soon, followed by insulating, and running in-slab radiant heat lines. After that we will pour the slab. Another reminder that second additional deposits will be due at slab pour.

Building 6: Gypcrete is poured and insulation has begun at unit 16. After completed they will move to unit 17 and finished at unit 18. Drywall will follow soon after insulation is all wrapped up.

Have a great weekend gang!

Great room ready for flooring
Drywall going up 2
Siding going up
Great room framed
Windows installed

Filed Under: Fish Hawk Landing News