Busy at work

Happy Friday everybody! Here is our weekly update:

Building 1: Baseboard, sills, and door casing has been installed at unit 1, and most doors have been hung at unit 1. Cabinet, bath, and door hardware install will begin soon. Electrical trim out has begun at unit 1 and will continue over the next few weeks at all three units.

Building 2: Unit 6 drywall is finished and painters have primed walls and ceilings. Drywall is hung in unit 5 and taping and mudding has begun.

Building 3: Rough electrical and rough plumbing is wrapped up at building 3. Insulation will begin here once it is finished at building 6.

Building 4: Timber framing and deck framing continues. Soffit is currently being installed and nearly all windows are installed.

Building 5: Back-out framing continues. Backfill of foundation will be next.

Building 6: Insulation has begun at unit 17. Once finished they will move to unit 18 and we will begin stocking drywall at unit 16.

Enjoy your weekend everyone!

Door to master
Stairway build out
Command center
A winter view

Filed Under: Fish Hawk Landing News