Hope y’all had a great week! Here is our weekly update:
Building 1: Unit 1 trim is completed and carpenters have moved to unit 2 to begin their trim install. Electrical trim will start back up this week at unit 1 and move to unit 2 once completed.
Building 2: Unit 5 walls have been drywalled and textured. Painters will be in there priming walls early next week. Drywall is currently being hung at unit 4.
Building 3: All roughs are complete. Insulation will begin next week.
Building 4: Plumbing rough-in will start next week. Once wrapped up at the first unit electricians will get in there to begin running wire.
Building 5: Foundation has been backfilled. Insulation will be next followed by in-slab radiant heat. After that we will look to pour slabs. Another reminder that second additional deposits will be due at slab pour.
Building 6: Framing corrections are on-going at unit 18. Insulation has wrapped up at unit 17 and will begin at unit 18 soon.
Have a good one ladies and gents!