Buyer’s Update – April 7th, 2023

April 7, 2023 by Fish Hawk Landing

Master bedroom

Friday is here! Happy weekend gang! Here is our weekly update:

Building 1: Interior wood trim continues to be installed at unit 2. Electrical trim is on-going at unit 1 and will move to unit 2 later this week. Boiler install is nearly completed at all three units.

Building 2: Painters have primed at units 6 and 5. Drywallers are currently taping and mudding in unit 4. They will texture next week and following soon after will be painters. Tile prep has begun in unit 6 and tilers will begin installing next week.

Building 3: Insulation is next up for unit 7. They will be insulating for the next couple weeks and we will begin stocking drywall.

Building 4: Plumbing roughs have begun at unit 10 and will continue at building 4 over the next couple weeks.

Building 5: Spray foam in-slab insulation will begin next week. 

Building 6: Insulation will be wrapped up soon at building 6. Once completed we will begin stocking drywall.

Enjoy the warm sunny weekend everyone!

Lower stairway
Shower roughed in
Walk in closet
Basement getting framed
All of the insulation
Mini Foundation

Filed Under: Fish Hawk Landing News