Happy Friday everyone! Here is our weekly update:
Building 1: Interior trim is on-going at building 1. Glass partitions have begun to be installed at unit 1 and will wrap up at units 2 and 3 early next week.
Building 2: Drywallers have finished their texturing and painters have primed walls and ceilings at all three units. Tilers have begun installing tile at units 6 and 5 and will move to unit 4 next week.
Building 3: Insulation will begin soon. After insulation is completed they will stock drywall and begin hanging.
Building 4: Plumbing rough-in is nearly wrapped up at unit 10 and will be moving to unit 11 soon.
Building 5: Spray foam in-slab insulation has wrapped and wire mesh has been installed. In-slab radiant heat lines have been installed and we are ready for slab pour. Barring delays, slab pour will be Thursday. Last reminder that second additional deposits will be due at slab pour.
Building 6: Drywall has been stocked at units 16 and 17. Drywall hanging will continue over the next couple weeks at all three units.
Have a great weekend everyone!