Winter ain’t over yet! After a brief glimpse into spring we’re back to a cold snow filled Summit County. But that didn’t slow down the work at Fish Hawk Landing! Another productive week in the books! Here is our weekly update:
Building 1: Interior trim is near completion at building 1 and will be wrapping over the next couple weeks. Glass shower partitions have been installed in the master bathrooms. Electrical trim out is near completion and plumbing trim will begin soon.
Building 2: Tilers continue their tile install at all three units. Carpenters will begin setting cabinets and doors soon.
Building 3: After insulation is completed at unit 18 insulators will move to building 3. After insulation is finished we will begin stocking drywall.
Building 4: Plumbing has wrapped up at unit 10 and is currently in progress at unit 11. Electricians will begin soon at unit 10.
Building 5: The slab has been poured at building 5. Framers are currently working on their back-out framing.
Building 6: Drywall has been taped, mudded, and textured at unit 16. Drywallers will begin hanging drywall at unit 17 next week. Painters will be following close behind priming units 16 and 17.
Enjoy a nice relaxing weekend everyone!