Hello Fish Hawk Family! Hope you’ve all had a great week! Road prep is currently underway at Fish Hawk Landing. Front patios have already been poured, then we will have a week of road prep, followed by preparing and pouring of valley pans, and finally we will be looking to pour asphalt throughout the site. Due to safety reasons and to minimize any potential disruptions, we have decided to temporarily suspend any on-site visits until the road work activity is completed. Thank you for your understanding and cooperation.
Building 1: Front doors have been set at all three units. Painters are currently working on their final paint at unit 1 and will move to unit 2 once completed. Plumbing trim out and electrical trim out continues at units 2 and 3.
Building 2: Luxury vinyl plank flooring has been installed at all three units and floor protection has been put in place. Countertop templates will be made next week and we can expect install to take place in a couple weeks. Carpenters will begin installing doors and trim soon.
Building 3: We’ve had a couple weeks of framing corrections on-going at building 3. Framing inspections are scheduled for next week to be followed by insulation install.
Building 4: Rough-in plumbing is on-going at unit 11. They will move to the final unit sometime next week. Electricians have begun prepping unit 10 and will start their rough in soon.
Building 5: Framers are wrapping up their back-out framing. Plumbers will begin here once they are finished at building 4.
Building 6: Drywall hanging will continue at unit 17 next week. Painters will begin prepping unit 16 for priming and painting soon.
Have a good one gang!