Happy Friday gang! Road work continues down at Fish Hawk Landing. The main road and all driveways & parking areas are fully prepped and ready for asphalt. Asphalt pour was scheduled for this week but due to issues at the asphalt plant they have moved us back to Thursday of next week for our asphalt pour. Barring any further delays, asphalt should harden enough to get traffic back on site by the second week of June.
Building 1: Painters have prepped for unit 3. Final paint will begin soon. Masons will continue their stone work next week. Rear patios have been prepped and will be formed and poured soon.
Building 2: Carpenters have set all doors at unit 4, most doors at unit 5 are set and they’ve begun setting doors at unit 6. Boilers are installed and will be fired up soon.
Building 3: Framing inspections are all passed at building 3. Insulation is scheduled to start at building 3 next week before asphalt is poured, and they will continue their work after asphalt is finished and cured.
Building 4: Electrical rough-in work continues at building 4, and will be on-going for the next few weeks.
Building 5: Rough plumbing continues at unit 13. Rough-ins will be on-going for the next few weeks.
Building 6: Painters have wrapped up their priming and painting at all three units. Tile prep has begun at all three units and tile install will begin soon.
Enjoy a nice relaxing weekend everyone!