Hope everyone had a great week! Here is our weekly update:
Building 3: Countertops have been templated and install will begin soon at all three units. Plumbing trim out will begin once countertop have been installed. Electrical trim is currently in progress at all three units.
Building 4: Tile prep us currently underway at building 4. LVP install will begin next week at all units. After LVP is installed we will begin setting cabinets and hanging doors.
Building 5: Insulation is installed at all three units. Drywall has passed inspection at units 13 and 14 and will be taped, mudded, and textured next week. Drywall hanging will begin soon at unit 15.
Building 6: All three units have been issued their Certificate of Occupancy and building 6 is now closed. Punchlist will be on-going over the next couple weeks.
Enjoy your weekends everyone!