Hope everyone is having a great week so far! Here is our weekly update:
NOTICE: We are preparing for the road work on site and due to the high volume of activity and large machinery moving around (in addition to the normal high volume of subs already on site) there are no site visits allowed until further notice. We anticipate that once the road work is completed, we can resume any required site visits from non-construction personnel.
Building 1: Front doors are currently being set at units 1 and 2. All three front doors should be installed by the end of the week. Painters are prepping at unit 1 for final paint. Plumbing trim-out has begun at unit 1 and will be wrapping up at all three units soon.
Building 2: Bathroom tile has been installed at all three units in building 2. Cabinets have been set and Luxury Vinyl Plank flooring is currently being installed at units 4 & 5. Countertops will be templated next week.
Building 3: Insulation will begin soon at building 3.
Building 4: Rough-in plumbing continues at building 4 in unit 11. Electricians will begin there rough-in work soon at unit 10.
Building 5: Framers continue to work on their back-out framing.
Building 6: Drywall continues at unit 17. Once completed they will move to unit 18 and painters will follow close behind priming and painting the walls and ceilings.
Enjoy the rest of your week everyone!