Happy Friday guys! After a full week of rain road work has unfortunately been delayed down at Fish Hawk Landing. We will keep our eyes on the forecast and continue road work when the weather permits. Once again, we will be suspending on-site visits until all road work activity is wrapped up. We appreciate your continued understanding and cooperation.
Building 1: Final paint is underway at unit 2. Once finished they will move to unit 3. Xcel has installed the gas meter at building 1 and once pipe is installed we will be able to fire up boilers. After in-floor heat is running we will be able to finish flooring and baseboard install on the first floor. Garage doors and openers have been installed at all three units.
Building 2: Countertop install will begin soon. Glass shower partitions will be installed next week. Garage doors and openers have been installed at all three units.
Building 3: We’re continuing with our framing corrections, inspections should be wrapped up sometime next week, then we will look to start installing insulation.
Building 4: Rough plumbing has begun at unit 12. Electricians will start running wire next week at unit 10.
Building 5: Framers have finished their back-out framing, plumbing rough-ins will begin soon.
Building 6: Drywall at unit 17 has been taped and mudded. They will begin texturing early next week. Drywall hanging has begun at unit 18. Garage doors and openers have been installed at all three units.
More rain on the way! Stay dry this weekend everyone!