News

Buyer’s Update – November 11th, 2022

November 11, 2022 by Fish Hawk Landing

The next unit going up

Temperatures are dropping in Summit County but the work down at Fish Hawk Landing keeps truckin’ along. Another bustling week in the books. Here is our weekly update:

Building 1: Insulation will be wrapped up soon at building 1. After insulation is completed we will start stocking drywall. Exterior siding has begun with installation of LP Smartside on the south end of the building and stone siding on the north end.

Building 2: Rough electrical is on-going at unit 5, and rough plumbing has now passed all inspections. Exterior siding has begun with installation of LP Smartside on the north end of the building.

Building 3: Framing on all three levels is completed and we’re now installing trusses. Once finished with truss installation we will move on to roof framing.

Building 4: Slab is prepped and ready for under-slab insulation. We will look to get insulation sprayed sometime next week. Just another reminder that second additional deposits will be due at slab pour.

Building 5: Interior footers have been poured and forms have been removed. After the interior of the foundation is backfilled we will begin underground plumbing.

Building 6: Rough plumbing continues at unit 16. Rough electrical will begin here once it is wrapped up at building 2.

Have a great weekend everyone!

A view from behind
Tyvek
Insulation going in
All of the insulation
The next foundation

Filed Under: Fish Hawk Landing News

Buyer Update – October 31st, 2022

October 31, 2022 by Fish Hawk Landing

Almost dried in for winter

Bust out your ice picks and shovels, wintertime is here in Summit County! Things are moving along steadily down here at Fish Hawk Landing. Here is our weekly update:

Building 1: Building 1 has passed framing inspection and we’re ready to begin the insulation process. We will start with air sealing which will be underway soon.

Building 2: Rough electrical continues in unit 5 and plumbing rough-in is now completed at building 2. All windows are now installed and the dry-in process has concluded.

Building 3: First floor wall framing has wrapped up, the second and third level subfloor has been completed, and framers will begin third level wall framing soon.

Building 4: Slab prep has finished and we’ll be moving on to under-slab insulation soon. Another reminder that second additional deposits will be due at slab pour.

Building 5: Building 5 has been backfilled and prepped for interior footers which will be formed and poured soon.

Building 6: Rough plumbing has begun at unit 16 in building 6. 

Enjoy your week and stay warm everyone!

The control switches
A sunny view to Buffalo
The Next Foundation
Rough Framing going up

Filed Under: Fish Hawk Landing News

Buyer’s Update – October 15th, 2022

October 15, 2022 by Fish Hawk Landing

Interior framing

Hope you all had a great week! Here is our weekly update:

Building 1: After a few framing correction we’ll begin our insulation work with air sealing.

Building 2: Rough electrical continues at unit 4. Plumbing is wrapping up at unit 5 and will be moving on to the final unit of building 2 next week.

Building 3: Building 3 slab has been poured and we’re now going vertical at our 4th building at Fish Hawk Landing. First floor wall framing will continue into next week.

Building 4: Slab prep will continue into next week to be followed by spray foam under-slab insulation.

Building 5:  Backfill will be soon. Interior footer pour will follow.

Building 6: Framing back-out is on-going.

Have an awesome weekend everyone!

Mechanical
A beautiful fall day
Utilities 1
Foundation down

Filed Under: Fish Hawk Landing News

Buyer’s Update – October 7th, 2022

October 7, 2022 by Fish Hawk Landing

The next building

Happy Friday Fish Hawk family! Here is our weekly update:

Building 1: Gypcrete has been poured in all three units. Insulation will begin next week.

Building 2: Rough plumbing is on-going. Rough electrical has begun at unit 4. The dry-in process will continue into the next couple week.

Building 3: Slab pour will be early Monday morning. One last reminder that your second additional deposits will be due at slab pour.

Building 4: Underground plumbing has wrapped up and passed inspection. Slab prep will be next. Another early reminder that second additional deposits will be due at slab pour.

Building 5:  Foundation walls have been poured and forms have been stripped. Backfill will be next followed by work on the interior footers.

Building 6: Soffit install is on-going and framing back-out is currently in progress. Deck framing is also on-going.

Have a great weekend everyone!

Entry way
Foundation laid
Radiant heat
Utilities

Filed Under: Fish Hawk Landing News

Buyer’s Update – September 30th, 2022

September 30, 2022 by Fish Hawk Landing

Laying out the next unit

Hope you all have been enjoying the fall colors this week! Here is our weekly update down at Fish Hawk Landing:

Building 1: Rough electrical has wrapped up and passed inspection. In-floor radiant heat lines have been run and also passed inspection. Gypcrete pour will be next.

Building 2: Rough plumbing continues. Window install and house wrap are also on-going. Deck framing is close to being wrapped up.

Building 3: Under-slab insulation has been completed and in-slab radiant heat lines have been ran. Barring the weather, slab pour will be sometime next week. Final reminder that second additional deposits will be due at slab pour.

Building 4: Underground plumbing continues. To be followed by our initial slab prep. Just an early reminder that your second additional deposits will be due at slab pour.

Building 5:  Footers have been formed and poured. Foundation walls are formed and ready to be poured early next week.

Building 6: Roof framing has wrapped up. Soffit is currently being installed. Deck framing is on-going.

Enjoy your weekend everyone!

Foundations going in
Punchlist
Getting plumbed
Coming together

Filed Under: Fish Hawk Landing News

Buyer’s update – September 17th, 2022

September 17, 2022 by Fish Hawk Landing

Hope you had a fantastic week. Here is our update this week.

Building 1: Rough electrical is nearing completion.

Building 2: Rough plumbing on unit 4 is nearing completion. Window install as well as house wrap is in progress. Deck framing is nearing completion.

Building 3: Underground plumbing is complete. Slab prep is complete as well. Underslab insulation is complete too.

Building 4: Underground plumbing is in progress.

Building 5:  Utilities are complete. Foundation excavation is in progress.

Building 6: Roof framing is complete. Deck framing is still in progress.

Have an awesome weekend!

Filed Under: Fish Hawk Landing News